The short version
- Two to four weeks on site is typical for a full bathroom.
- Order tile, the vanity and fixtures before demolition starts.
- Custom shower glass is measured after the tile is finished, so it’s always last.
Before work starts: planning and ordering
The clock that matters starts before anyone picks up a tool. Vanities, tile, fixtures and shower valves can take anywhere from days to several weeks to arrive. A well-run job has everything on hand, or on a confirmed delivery date, before the old bathroom is torn out.
If your project moves plumbing or adds a bathroom, this is also when the permit is applied for.
Week one: demolition and rough-in
- The old tub, tile, vanity, toilet and flooring come out.
- With the walls open, the plumbing and framing are checked. This is when hidden water damage or worn-out pipes show up.
- New drains, supply lines and the shower valve go in. Electrical rough-in is done for lighting, the fan and any floor heat.
- Where a permit applies, the rough-in is inspected before the walls are closed.
Week two: walls, waterproofing and tile
- Backer board goes up in the wet areas and moisture-resistant board elsewhere.
- The shower or tub surround is waterproofed as one continuous system. This step can’t be rushed, because some products need time to cure.
- Floor and wall tile begins.
Week three: tile, grout and fixtures
- Tile is finished, grouted and sealed where needed.
- The room is painted.
- The vanity, counter, toilet, faucet and shower trim are installed and connected.
- Mirror, lighting, fan cover and accessories go on.
Week four: glass and final details
Custom shower glass is measured only after the tile is complete, because it has to fit the finished opening exactly. It’s then made to order and installed, usually a week or two later. The bathroom is fully usable in the meantime with a temporary curtain.
The job ends with a walkthrough: every fixture tested, every caulk line checked, and anything that isn’t right put right.
What stretches the timeline
- Hidden damage. Rotten subfloor or failed plumbing has to be fixed before anything new goes in.
- Special-order items that arrive late or damaged.
- Changes made after work has begun.
- Moving the toilet or shower drain, which is more involved than moving a sink.
- Waiting on inspections, where a permit applies.
Older homes are the usual source of surprises. If yours was built before 1960, it’s worth reading what tends to turn up behind the walls before you set a budget.
If it’s your only bathroom
Say so at the first visit. The work can be sequenced so the toilet is out of service for the shortest time possible, and the dates you’ll be without a shower can be planned around. Knowing in advance is what makes it manageable.
See how we approach bathroom renovations.
Sources